Processing of application for New Services / Additional Loads from where network expansion required in APCPDCL-11KV(01-04-2021 to 30-06-2021)
Division Number of Applications 11kv Min Duration(Days) 11kv Max Duration(Days) 11kv Average Duration(Days) 11kv Applications Processed(%) 11kv WRT
CRDA 1 8 8 8.00 100.00 1
ONGOLE 4 7 7 7.00 100.00 4
VIJAYAWADA 88 2 164 86.13 7.95 7
TOTAL 93 2 164 33.71 12.90 12