Processing of application for New Services / Additional Loads from where network expansion req uired in APCPDCL-11KV(01-04-2021 to 30-06-2021)
S.NO Subdivision Number of Applications 11kv Min Duration(Days) 11kv Max Duration(Days) 11kv Average Duration(Days) 11kv Applications Processed(%) 11kv WRT
1 CHILAKALURI PET 1 8 8 8.00 100.00 1
2 MARTUR 1 7 7 7.00 100.00 1
3 ONGOLERURAL-I 2 7 7 7.00 100.00 2
4 ONGOLERURAL-II 1 7 7 7.00 100.00 1
5 HANUMAN JUNCTION 24 13 160 86.83 12.50 3
6 GUNADALA 1 37 37 37.00 0.00 0
7 PATAMATA 1 122 122 122.00 0.00 0
8 MACHILIPATNAM 1 71 71 71.00 0.00 0
9 MTM_RURAL 6 45 106 95.83 0.00 0
10 PEDANA 34 2 164 86.15 8.82 3
11 TIRUVURU 8 96 96 96.00 0.00 0
12 VISSANNAPET 2 98 110 104.00 0.00 0
13 DISTRIBUTION II 2 2 91 46.50 50.00 1
14 VIJAYAWADA C AND O D3 9 51 94 86.89 0.00 0