Processing of application for New Services / Additional Loads from where network expansion req uired in APCPDCL-11KV(01-04-2021 to 30-06-2021)
S.No Section Number of Applications 11kv Min Duration(Days) 11kv Max Duration(Days) 11kv Average Duration(Days) 11kv Applications Processed(%) 11kv WRT
1 TOWN-II CH.PET 1 8 8 8.00 100.00 1
2 BALLIKURVA 1 7 7 7.00 100.00 1
3 MADDIPADU 1 7 7 7.00 100.00 1
4 MCHPALEM 1 7 7 7.00 100.00 1
5 ONGOLE RURALS 1 7 7 7.00 100.00 1
6 HANUMAN JUNCTION 1 160 160 160.00 0.00 0
7 TELEPROLU 15 93 93 93.00 0.00 0
8 UNGUTURU 5 74 142 98.00 0.00 0
9 VEERAVALLI 3 13 13 13.00 100.00 3
10 GANNAVARAM 1 37 37 37.00 0.00 0
11 RINGROAD 1 122 122 122.00 0.00 0
12 D3 MTM 1 71 71 71.00 0.00 0
13 MTM RURALS 6 45 106 95.83 0.00 0
14 KRUTHIVENNU 34 2 164 86.15 8.82 3
15 TIRUVURU RURAL 8 96 96 96.00 0.00 0
16 CHATRAI 1 98 98 98.00 0.00 0
17 VISSANNAPETA 1 110 110 110.00 0.00 0
18 GOVERNORPET 2 2 91 46.50 50.00 1
19 MOGHALRAJPURAM 8 73 94 91.38 0.00 0
20 SURYARAOPET 1 51 51 51.00 0.00 0
21 Grand Total 93 2 164 82.84946237 12.90322581 12