Processing of application for New Services / Additional Loads from where network expansion req uired in APCPDCL-11KV(01-04-2021 to 30-06-2021)
S.NO Division Number of Applications 11kv Min Duration(Days) 11kv Max Duration(Days) 11kv Average Duration(Days) 11kv Applications Processed(%) 11kv WRT
1 GUNTUR-TOWN2 1 8 8 8.00 100.00 1
2 ADDANKI 1 7 7 7.00 100.00 1
3 ONGOLE 3 7 7 7.00 100.00 3
4 GUDIVADA 24 13 160 86.83 12.50 3
5 GUNADALA 2 37 122 79.50 0.00 0
6 MACHILIPATNAM 41 2 164 87.20 7.32 3
7 NUZVIDU 10 96 110 97.60 0.00 0
8 VIJAYAWADA TOWN 11 2 94 79.55 9.09 1