Conversions from LT Single phase to 3 phase done in APCPDCL(01-04-2021 to 30-06-2021)
Section Number of Requests PH Min of Difference between Date of Complaint & Date of Redressal in Hours Max of Difference between Date of Complaint & Date of Redressal in Hours Average of Difference between Date of Complaint & Date of Redressal in Hours Requests Handled(%) PH WRT
MANDADAM 1 29 29 29 100 1
RAYAPUDI 2 29 29 29 100 2
KRISHNANAGAR 1 29 29 29 100 1
KUNCHANAPALLI 2 29 29 29 100 2
MANGALAGIRI-RURAL 2 29 29 29 100 2
EDLAPADU 1 29 29 29 100 1
GANAPAVARAM 1 29 29 29 100 1
TOWN-I CH.PET 3 29 29 29 100 3
TOWN-II CH.PET 1 29 29 29 100 1
BAPATLA-TOWN 1 30 30 30 100 1
KARLAPALEM 1 30 30 30 100 1
CHERUKUPALLI 1 30 30 30 100 1
PONNUR-TOWN 3 30 30 30 100 3
D3-GUNTUR 1 30 30 30 100 1
D11-GUNTUR 4 30 30 30 100 4
D4-GUNTUR 4 30 30 30 100 4
D7-GUNTUR 5 30 30 30 100 5
D8-GUNTUR 1 30 30 30 100 1
D12-GUNTUR 4 30 30 30 100 4
D2-GUNTUR 1 30 30 30 100 1
D6-GUNTUR 1 30 30 30 100 1
LINES-GUNTUR 6 30 30 30 100 6
D5-GUNTUR 1 30 30 30 100 1
D9-GUNTUR 1 30 30 30 100 1
PEDAKAKANI 1 30 30 30 100 1
DACHEPALLI-TOWN 2 30 30 30 100 2
KAREMPUDI 2 30 30 30 100 2
MACHERLA-TOWN 2 30 30 30 100 2
SATTENAPALLI-TOWN 2 30 30 30 100 2
VINUKONDA-RURAL 1 30 30 30 100 1
REPALLE-TOWN 1 30 30 30 100 1
AMRUTHALURU 3 30 30 30 100 3
CHEBROLU 2 30 30 30 100 2
AE-RURALS 1 30 30 30 100 1
TENALI-D1 6 30 30 30 100 6
TENALI-D2 5 30 30 30 100 5
TENALI-D3 2 30 30 30 100 2
D1 CHIRALA 5 0 7 4.2 100 5
VETAPALEM 2 0 30 15 100 2
ULAVAPADU 1 7 7 7 100 1
DARSI 1 7 7 7 100 1
DARSI RURALS 1 7 7 7 100 1
D4 ONGOLE 3 7 7 7 100 3
ONGOLE RURALS 5 7 7 7 100 5
Grand Total 97 0 30 25.60824742 100 97